Trial Engine Run on the newly laid Indore-Rajendra Nagar track (Indore-Dahod line). WR has been granted 6 months' extension by the IR to convert Indore-Mhow GC and complete the Indore-Tihi BG line.
Courtsey - Naidunia Epaper, Indore
Courtsey - Naidunia Epaper, Indore
2 Posts
#indorenews
1. News update regarding Island Platform's incomplete work at Indore..
2. News regarding tunnel work near Tihi in the second phase work of Indore-Dahod line..
1. News update regarding Island Platform's incomplete work at Indore..
2. News regarding tunnel work near Tihi in the second phase work of Indore-Dahod line..
As usual IR not showing any sensitivity toward previously committed dates..and extension date ka daur start ho gaya ...
Kuch naya add karo. Kitna kaam hua h.indore pltfrm or island ready hua ya nhi
Railway ne sayad phir slow speed pakad li.
Railway ne sayad phir slow speed pakad li.
January Se Pahle muskil hai already they have send the request to increase the time for this project