#electrification #Patiala #Jakhal The foundation stone for electrification of Jakhal-Dhuri-Ludhiana shall be laid in last week of December 2015, and for Rajpura-Patiala-Dhuri-Lehra Mohabat , it shall be laid in January 2016.
As mentioned earlier, Rajpura-Patiala-Dhuri-Lehra Mohabat got delayed over a month cuz of FLS and other related works like planning for doubling.
As mentioned earlier, Rajpura-Patiala-Dhuri-Lehra Mohabat got delayed over a month cuz of FLS and other related works like planning for doubling.
1 Public Posts - Sun Nov 22, 2015
electrification shall be done for single line (for Rajpura-Patiala-Dhuri-Lehra Mohabat ) and the doubling work shall be running parallel to it. , for Jakhal-Dhuri-Ludhiana the doubling has not been sanctioned yet, but you can eye for it in the next budget (hopefully). Foundation for Jakhal-Dhuri-Ludhiana may come near Gill station on DUI-LDH section. The contractor has already finished the site survey from JKL-DUI. For Rajpura-Patiala-Dhuri-Lehra Mohabat the contractor may get the LOI in coming 3-4 days and they shall start the site survey of it also in the coming few days , they'll speed-up the work here and shall expedite with Jakhal-Dhuri-Ludhiana.
As mentioned earlier, the Jakhal-Dhuri-Ludhiana is going to be on high rise OHE lately.
RVNL...
more...
As mentioned earlier, the Jakhal-Dhuri-Ludhiana is going to be on high rise OHE lately.
RVNL...
more...
14 Public Posts - Sun Nov 22, 2015
1 Public Posts - Mon Nov 23, 2015
2 Public Posts - Thu Nov 26, 2015
1 Public Posts - Fri Nov 27, 2015
3 Public Posts - Fri Dec 04, 2015
2 Public Posts - Sun Dec 20, 2015
1 Public Posts - Wed Dec 23, 2015