Dear Moderator and Admins, can we now add " Doubling of Single Diesel BG " also to Rajpura-Bathinda section of NR. The Final Locations Survey is going on and main tender is also expected by this month end. The project is also under fast track execution.
Any new information regarding electrification of these 3 railway track.
Why ? Jakhal-Dhuri-Ludhiana foundation was laid. Work should be starting by Mid January.
PMC tender is yet to be opened on 11th. All works wil start after that.
PMC tender opening date has been extended until 27th January from 11th January