Is there any Plan for Double track between Hyderabad and Bangalore.
Doubling and Electrification of SC-GTL via Wadi,Raichur is almost complete. Tenders have been floated for YNK-DMM doubling. GY-DMM is electrified, but doubling work is yet to start.
I heard that electrification between Guntakal-Wadi would be done by June 2016. Hope Guntakal Yelhanka also doubles on war path.. have seen the work already started which is good sign!