#Electrification update GKP-BST.
bst-kld under wire, kld stn 10% wrk remain, kld-maghar no tighten wire, maghar-jagatbela no wire, jagatbela-dmg wired, uppr wire work done lower wire clip need 2 be done fr wired section. 6 more months to be taken as per assum.
bst-kld under wire, kld stn 10% wrk remain, kld-maghar no tighten wire, maghar-jagatbela no wire, jagatbela-dmg wired, uppr wire work done lower wire clip need 2 be done fr wired section. 6 more months to be taken as per assum.
15 Public Posts - Sat May 14, 2016
1 Public Posts - Sun May 15, 2016
2 Public Posts - Tue May 31, 2016
But now they are agreeing on delay and assuring to complete pending work by Jul;2016