Shashank^~ 7685 blog posts#ETALDELECTRIFICATION update.
OHE fully installed in JBP-NU section. 95% work completed.
Electrification work ongoing in NU-PPI section.
Update- Added a few more pics :)
OHE fully installed in JBP-NU section. 95% work completed.
Electrification work ongoing in NU-PPI section.
Update- Added a few more pics :)
3 Posts
Indeed! Already the PPI-ET section is fitted with poles and catenary (stations are left). NU-PPI section is still barren of poles. But JBP-NU section is racing very ahead of them. Pics are evident.
You are right! But Jabalpur deserves electrification. It is the H.O. of WCR and has been neglected for the past few decades. We'll soon witness electric locomotives on this section but, the EMD's will surely be preferred for the freight b'cause of their better performance.
Cheers man!
Cheers man!
nice to see the completed section of JBP (Bhedaghat)-NU and hope to see these type of more pics of NU-PPI section and still waiting to see the electrification at main stations like JBP,NU,PPI
Electrification of NU-PPI section is awaited. As for the main stations such as JBP, I wonder when will the work start.