#DoublingUpdates
Mohol-Madha 30Km second line is ready with all infrastructure and signals, waiting for inspection.
Madha-Kurduwadi 16Km Leveling done, construction and second line work is in progress.
Kurduwadi-Jeur 34Km Leveling is in progress.
Jeur-Bhigwan...
more...
Mohol-Madha 30Km second line is ready with all infrastructure and signals, waiting for inspection.
Madha-Kurduwadi 16Km Leveling done, construction and second line work is in progress.
Kurduwadi-Jeur 34Km Leveling is in progress.
Jeur-Bhigwan...
more...