Jul 04 2016 (15:08) NJP/New Jalpaiguri Junction (8 PFs)
Kanishk Mitra~
Kanishk Mitra~ 2461 blog postsSections Targeted for Electrification during 2016-17
.
No Electrification Project for NFR under project office New Jalpaiguri for 2016-17
.
Link: click here
.
No Electrification Project for NFR under project office New Jalpaiguri for 2016-17
.
Link: click here
SNRR-JBP and JBP-ET in the list with marginal 90 Kms ro complete the section.
so after reviewing this list we can expect the completion of ET-JBP route electrification by dec 2016 and JBP-ALD by 2017 and where is sansarpur located its also shown in the list???
Sansarpur is in KTE-JBP section. Dec 2016 possible nahi h. Mar 2017 shayad expect kar sakte h.