MUNIRABAD-RAICHUR( GINIGERA-GANGAVATHI=45KM) NEW LINE 165KM UPDATE:
1.TRACK COMPLETED FROM GINIGERA TO CHIKKABENKAL STATION=27KM
2.FROM CHIKKABENKAL TO GANGAVATHI GROUND LEVELING COMPLETED BUT YET TO PLACE SLEEPER BEDS=13KM
3.FROM GANGAVATHI TO TOWARDS RAICHUR GROUND LEVEL WORK GOING ON ABOUT 4KM
4....
more...
1.TRACK COMPLETED FROM GINIGERA TO CHIKKABENKAL STATION=27KM
2.FROM CHIKKABENKAL TO GANGAVATHI GROUND LEVELING COMPLETED BUT YET TO PLACE SLEEPER BEDS=13KM
3.FROM GANGAVATHI TO TOWARDS RAICHUR GROUND LEVEL WORK GOING ON ABOUT 4KM
4....
more...
1 Public Posts - Thu Oct 27, 2016
3 Public Posts - Fri Oct 28, 2016
I don't think swr do this ..it s only possible by next year end ..After completion of gangavathi railway station then only swr thinks introduce new train on this route ..untill then no hopes