Status of Harbour Line Extention till Goregaon:-
1.Tracks Laying Completed
2.Electrification of Andheri-Ram Mandir Section Remaining
3.Extention of Harbour Line Platform of Ram Mandir Station for 12 Car Local is going on
1.Tracks Laying Completed
2.Electrification of Andheri-Ram Mandir Section Remaining
3.Extention of Harbour Line Platform of Ram Mandir Station for 12 Car Local is going on
3 Public Posts - Fri Sep 15, 2017
1 Public Posts - Sat Sep 16, 2017
RMAR Harbour Line PFs were Earlier Constructed to Accommodate 9 Car Locals But Now PFs Extension is in Progress to Accommodate 12 Car Local and the Line is Going till Goregaon East-West Flyover These Lines will Be Used to Park Local Trains