so at last OHE poles with OHE wires reached KEQ and hopefully will reach JBP also very soon so good pace was seen in efication work after ET-PPI work completion and hope by oct 2017 we can hope PPI-JBP section work shud b completed and P7,WAP4,WAG9 etc. machos will arrive JBP soon and it will be a historic...
more...
#ETALDELECTRIFICATIONUPDATES
#PPIJBPELECTRIFICATIONUPDATES
so at last OHE poles with OHE wires reached KEQ and hopefully will reach JBP also very soon so good pace was seen in efication work after ET-PPI work completion and hope by oct 2017 we can hope PPI-JBP section work shud b completed and P7,WAP4,WAG9 etc. machos will arrive JBP soon and it will be a historic...
more...
1 Posts
KLraat m h dkha me
Poles lg the h Kuch Kuch jgah
No wires ksne Kha ??
Poles lg the h Kuch Kuch jgah
No wires ksne Kha ??
wires k baare me to news me aaya hai or KEQ godown k aage tak poles with wires lag gaye hai aisa news me hai
Bhai Hm to apni ankho se dkhe
Koi wires nhi aye h
Plus phle jha tk poles the wha se kachpura ki building tk koi poles nhi h
Phr building se mal godam tk poles h pr avi bs foundation m rkhe gye h unko set nhi kia h
Koi wires nhi aye h
Plus phle jha tk poles the wha se kachpura ki building tk koi poles nhi h
Phr building se mal godam tk poles h pr avi bs foundation m rkhe gye h unko set nhi kia h
JBP-BTC me JBP-Ghnsore tak BG traffic chalu ho gya hai or ab GNS-NR k bich CRS due hai along with samnapur-BTC or gwarighat me electrification k equipments ka dumping ground set ho rha hai or electrification ka kaam KEQ se shuru ho gaya hai kyunki iss anunual yr me KEQ-GNS tak electrification complete krne ka target hai