Major bridge being constructed across Narmada Canal b/w Surendranagar and Chamaraj stations. Track linking,minor bridges,major bridges,earthwork in progress b/w Surendranagar and Chamaraj and also b/w Wankaner and Than.
Surendranagar Chamaraj Feb 2018 tak complete ho jaayega. Bileshwar Rajkot last mein Double hoga.
Targets for each FY-
Surendranagar Chamaraj Feb 2018
Chamaraj Daladi Mar 2019
Daladi Kankot Mar 2020
Kankot...