** Itarsi - Jabalpur Electrification Detailed Update **
1. Itarsi- Pipariya (67 KMS): Double Electric Line. Electric locos already plying.
2. Pipariya-Salichauka Road (36 KMS):- Poles erected. Clippers installed. Catenary along with contact wire installed. Tightening done. Work at stations done. (Completed)
3. Salichauka Road - Bohani (27 KMS):- Poles erected. Clippers installed. Catenary wire along with contact wire installed, except in few patches....
more...
1. Itarsi- Pipariya (67 KMS): Double Electric Line. Electric locos already plying.
2. Pipariya-Salichauka Road (36 KMS):- Poles erected. Clippers installed. Catenary along with contact wire installed. Tightening done. Work at stations done. (Completed)
3. Salichauka Road - Bohani (27 KMS):- Poles erected. Clippers installed. Catenary wire along with contact wire installed, except in few patches....
more...
11 Public Posts - Sun Sep 24, 2017
Agar CORE change toh 1 month is enough for electrifying JBP yard and station. But I guess jab tak pressure nahi padega, kaam delay hoga. That's why I said 2 months after taking some margin.