Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 #
 Rating
 Correct
 Wrong
 Stamp
 PNR Ref
 PNR Req
 Blank PNRs
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt

RailCal app

site support

हाटे-बाजारे एक्सप्रेस : चलती - फिरती मछली बाजार - Piyush Singh

Search Forum
<<prev entry    next entry>>
Blog Entry# 2767128
Posted: Nov 15 2017 (13:03)

No Responses Yet
General Travel
798 views
2

Nov 15 2017 (13:03)  
guest
Entry# 2767128              
Biggest Gauge Conversion projects of IR currently going/to be taken up. (These projects are Biggest because after completion the BG line will usher development drive).
1. JBP-NIR-BTC along with NGP-CWA-NIR-MFR. Status:- JBP-NIR is Single BG line & operational uptill Ghunsore. NGP-CWA works going on.
2. IND-KNW-AK. IND-DADN(MHOW) is Single BG line & fully operational. Sanawad-Khandwa leg is in conversion process.
3. UDZ-ADI. Works in
...
more...
ADI-HMT leg is partialy completed. UDZ-RJSM(Rajsamand) leg works started slowly.
4. MJ-MVJ. Work is waiting to start in NDT-MJ leg. NDT-MVJ leg completed & operational.
5. BPR-PBE-SPZ/MLN-STP-ASH. BPR-PBE-TPU leg completed

Translate to English
Translate to Hindi
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy