Tender is out for the electrification of Hosapete - Hubballi - Tinaighat section of UBL division - SWR.
Ref:...
Ref:...
Expedite the electrification works on warfooting. 2 Year completion period shall be reduced to 18 month period.
For package-1-Hospet-Torangallu-kudatini=45km Double line=45*2=90km
& Torangallu-Ranjitpura=22Km Single line
So total for 112Km need 24 Months to Finish RE?
& Torangallu-Ranjitpura=22Km Single line
So total for 112Km need 24 Months to Finish RE?
Still doubling is not completed in some parts of Hpt-Ubl-Clr section like Ubl-Dwr, Bnp-Kbl, etc which may delay electrification work