The electrification of Erode-Karur-Tiruchirapalli and Salem-Karur-Dindigul should be changed to 150 now. Because on 2nd and 3rd February CRS will be conducted for Erode-Karur-Trichy 140 kms. After that only Salem-Karur-Dindigul will be left. The work between Karur-Dindigul is in advance stage and is in fast pace. Also the work between Trichy-Thanjavur-Karaikal will get over by March 2019.