Yesterday 05-Feb-2018 single loco (Light loco) run successfully completed at the speed of 30Km/hr at ASH/Aishbagh - STP/Sitapur section. As per NER officials by Mar;2018 gauge conversion would be completed so CRS can be requested in month of May;2018. Post successful CRS commencement of passenger train can be started.
1 Public Posts - Tue Feb 06, 2018
2 Public Posts - Thu Feb 08, 2018
2 Public Posts - Sat Feb 10, 2018
7 Public Posts - Mon Feb 12, 2018
2 Public Posts - Tue Feb 13, 2018
May be if everything goes well then we can expect first train from ASH to MLN In the month of September or October.. Waiting for further news from NER.. After 20th March everything will be clear I think