Work at diamond crossing near STP/Sitapur and SCC/Sitapur Cantt. in in full swing (More than 25 to 30 workers been seen) and most probably it would be completed with in 10 days as track laying almost completed so NER may take mega block for interlock for diamond crossing soon. Same time doubling of SCC/Sitapur Cantt. - BUW/Burwhal is on going which would ease NER work to priorities diamond crossing as well as doubling.
-
***Next trial run from ASH-STP is scheduled on 06-Mar-2018***
-
***Next trial run from ASH-STP is scheduled on 06-Mar-2018***
That means before 6march all the track work would be completed and if everything goes well then we can expect CRS in April or May..