I'm traveling in hampi exp. Hpt - ubl doubling update part of vsg - hpt doubling : good news is that doubling of 5 kms at city entrance of koppal completed successfully ..new Rob under construction at kbl ..now only 500mts work at munirabad and about 10 kms at gdg track laying is left ...ill update gdg work shortly
So Koppal-Ginigera section both lines are being used?
And what about Ginigera-Hitnal, both lines are being used?
And what about Ginigera-Hitnal, both lines are being used?
Not yet..doubling completed btn koppal - munirabad but few signaling and engine rolling work left I think ..maybe after 3 months