Gonda jn GC Update.....PF 4 ,5
As of now platform works and signals are almost completed....floor work is in progress ...
Gonda yard remodeling work will be completed by the end of this month....
As of now platform works and signals are almost completed....floor work is in progress ...
Gonda yard remodeling work will be completed by the end of this month....
6 Public Posts - Mon Mar 12, 2018
1&2 up track and 4&5 down track hoga 3A&3B locals ko handle karega. Waise bhi 3B ko extend kiya ja rha hai. Toh short length ki train handle ho jayegi.
Fil haal 161 train ko handle karne k liye itte kafi hai.
Aur future dmu station ban jane se Junction par load kum ho jayega
Fil haal 161 train ko handle karne k liye itte kafi hai.
Aur future dmu station ban jane se Junction par load kum ho jayega
1 Public Posts - Mon Mar 12, 2018
1 Public Posts - Tue Mar 13, 2018