Search Forum
Blog Entry# 3197923
Posted: Mar 12 2018 (22:40)
9 Responses
Last Response: Mar 13 2018 (13:40)
9 Responses
Last Response: Mar 13 2018 (13:40)
Gonda jn GC Update.....PF 4 ,5
As of now platform works and signals are almost completed....floor work is in progress ...
Gonda yard remodeling work will be completed by the end of this month....
As of now platform works and signals are almost completed....floor work is in progress ...
Gonda yard remodeling work will be completed by the end of this month....
5 Posts
Plan drop ni hua hai. Bus thoda time lagega jab tak ki new cabin me shifting ni ho jaye.
1&2 up track and 4&5 down track hoga 3A&3B locals ko handle karega. Waise bhi 3B ko extend kiya ja rha hai. Toh short length ki train handle ho jayegi.
Fil haal 161 train ko handle karne k liye itte kafi hai.
Aur future dmu station ban jane se Junction par load kum ho jayega
Fil haal 161 train ko handle karne k liye itte kafi hai.
Aur future dmu station ban jane se Junction par load kum ho jayega
Wo toh hai wahing pit ko yard me sift kar k ek aur island platform bana dena chahiye tha.