Doubling work of Vakav - Madha - Wadsinge - Kurduwadi is 95% completed.
Sleepers and track laid between Kurduwadi - Dhavlas (40% work completed) - Kem (75% completed) - Bhalawani - Jeur (30% work completed)
Rest Jeur - Bhigwan section leveling is in progress..!!
Sleepers and track laid between Kurduwadi - Dhavlas (40% work completed) - Kem (75% completed) - Bhalawani - Jeur (30% work completed)
Rest Jeur - Bhigwan section leveling is in progress..!!
Track laid between Kurduwadi to Kem and track for another loop line laid at Dhavlas.
Kem to Jeur leveling is completed.
Jeur to Bhigwan very slow work.. absolutely no progress I can say.. If work goes by this way, it will take another 3-4 years to complete Jeur - Bhigwan.
Kem to Jeur leveling is completed.
Jeur to Bhigwan very slow work.. absolutely no progress I can say.. If work goes by this way, it will take another 3-4 years to complete Jeur - Bhigwan.
Yes.. basically it is Ujani Dam backwater & Bhima River. So they might face difficulties in that. Work in progress very slowly..