Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 #
 Rating
 Correct
 Wrong
 Stamp
 PNR Ref
 PNR Req
 Blank PNRs
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt

RailCal app

site support

Mumbai Local - RailFanning nirvana.

Search Forum
<<prev entry    next entry>>
Blog Entry# 3260713
Posted: Apr 01 2018 (20:27)

5 Responses
Last Response: Jun 17 2018 (22:35)
Rail Fanning
11505 views
5

Apr 01 2018 (20:27)   UDZ/Udaipur City (5 PFs)
susmits~
susmits~   337 blog posts
Entry# 3260713            Tags   Past Edits
Engineering works status on the UDZ-COR section.
(As of April 1, 2018)
-
Level crossing elimination
* Level crossing elimination work ongoing between KLH and PMO.
*
...
more...
This excludes some sections between FAN and BSJ, and BSJ and KIN, where the track is 110 kmph capable.
* DRB to KLH is almost LC-free and trains run at around 80 kmph.
* Ex PMO to GSD and beyond is LC-free and 110 kmph-capable.
* One LC remains between GSD and COR (near milepost 2.5).
-
Electrification - Foundation work
* No foundation work between UDZ and KLH (incl.)
* Foundation work complete between ex KLH and milepost 72.5.
* Foundation work in progress between milepost 72.5 and 71.5, with digging complete and foundation material lying next to the pits.
* No foundation work between mileposts 71.5 and 64.1. This includes MVJ.
* Complete foundation work between mileposts 64.1 and 57.7 (ex. FAN).
* Complete foundation work between mileposts 53.3 and KIN (incl.) This excludes a 1 km block immediately preceding BSJ, though works at BSJ are complete.
* Complete foundation work between about 6 km after KIN and immediately before PMO.
* Complete foundation work between 1 km after PMO and 5 km before GSD.
-
Electrification - Pole work
All of the following is presently only complete as far as erecting electrical poles. There are no wire supports or wires at the moment.
* End of the KIN platform to about 6 km after KIN.
* About 5 km before GSD to milepost 1.7 (immediately preceding the approach signal at BEC).

Translate to English
Translate to Hindi

1 Public Posts - Sun Apr 29, 2018

3713 views
3

May 27 2018 (20:24)
susmits~
susmits~   337 blog posts
Re# 3260713-2               Past Edits
Updates for the month of May. Now with more potato-quality pictures featuring meme-level motion blurring.
.
Electrification - Foundation Work
* Some more foundation work between Khemli and Debari, but not very significant progress here.
*
...
more...
Foundation work on Khemli station and the adjoining CONCOR depot is making good progress.
* The stretch between Khemli and Mavli is almost complete, with perhaps a dozen or so foundations that have been dug but not cemented.
* Work at Mavli Junction proper has finally begun! And not a moment too soon, given that the rains are just a month away.
.
Electrification - Pole Work
* Major progress at Kapasan station. The majority of the station has poles, and they seem to be treating it as some sort of a local depot for poles. Maybe next month, I'll report polework between Kapasan and Bhupal Sagar!
* With the exception of Pandoli station (and possibly Netawal station which I didn't get a chance to observe), there's now total pole work between Kapasan and Chittorgarh bypass.
* This includes Ghosunda station, where, barring a half dozen poles, all poles have horizontal struts attached.
* For about 2.8 kilometres starting at mark 13/5 (about 3.5 km outside Ghosunda), free-hinged wire supports with insulation have been affixed to the poles.
.
Electrification - Related Works
* The parapet at Mavli that marked the site of the traction substation now stands surmounted with a metal fence. Kids still find ways to sneak in and were using the well-leveled area as an impromptu cricket field.
.
Overall, there's been pretty significant work over the past month. I've gone from viewing the December target with pessimism to guarded, cautious optimism. While I'm a little skeptical about Udaipur, perhaps we'll see a CRS between Chittorgarh and Khemli early next year.
.
It's a good thing that there has been so much effort on polework. During the high rainfall months of July, August, and September, work on wiring in these sections can take place once the severe thunderstorms and squalls have settled down.
.
Finally, there is no progress of any kind past the NWR-WR boundary near Berach Junction. Western Railway doesn't feel like waking from its slumber quite yet.

Translate to English
Translate to Hindi

3 Public Posts - Sun Jun 17, 2018
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy