As per 6 months back Google maps we can see their is ballast put on along the bed on small groups with some distance especially near the NTPC and after Basavan Bagewadi plant but still it have lot of works to do between Minchinal-wandal=71 km so they might be divided it as 32+39 so first target is Minchinal-Jumanal=32km and later after successful commision of that they go for commissionin of Jumnal-wandal=39km but mean while hope both targetted sections works going on together... We can see the update if Mr dhananjay done video after wandal upto Bijapur.
Ballast, sleepers, land levelling, new PF / bridges construction everything even if they are done; its the availability of rails that causes delay.
I am skeptical about the target being met.
I am skeptical about the target being met.
Yup for that one is said we can get update after we get video for Post wandal until Minchinal if lucky. Because last time they laid tracks for Lachyan-Minchinal and work was going on for bridges mean while so this time if they did so then no problem of tracks avalibilty too and i think this Doubling get priorty for tracks as its in contract with NTPC to finish as soon as possible by SWR
Will upload the remaining parts soon. Track laying work begins only after Bijapur. Sleepers were being unloaded from trucks on Jumnal Bijapur stretch.
As per Mr dhananjay Video for Honaganahalli-Bijapur i saw sleepers are being unloaded and some are placed beside Bedding and after Bijapur i saw already sleepers laid and also tracks fixed for some patches but as we discussed deficinecy of track may delay this one but already for Bijapur-Minchanal i think they got tracks from IR now they may get for Bijapur-Jumnal strect too. But jumnal-Wandal stretch only earth works finished still sleepers not reached in this strecth may be after some month they load sleepers here too and i dont think their will be deficincy of tracks for this doubling as earlier told its In central govt NTPC PSU and also IR which both tracking this doubling and also Customer funding done so no any hurdles will come i guess..