Info Update on Doubling Works between Dhone Jn/DHNE - Pendekallu Jn/PDL and Gooty Jn/GY - Dharmavaram Jn/DMM sections.
Pic 1,2,3 and 4 - Display the progress of works between DHNE - PDL. Ground leveling work is in progress with some intermediate gaps due to hills, mounds and some waterways.
Pic 5 to 23 - Display the progress of works between GY - KLU. Ground leveling work is mostly done, sleepers and gravel has been stashed along side of track and the bridge work across the Penna River at KLU is almost done.
Pic...
more...
Pic 1,2,3 and 4 - Display the progress of works between DHNE - PDL. Ground leveling work is in progress with some intermediate gaps due to hills, mounds and some waterways.
Pic 5 to 23 - Display the progress of works between GY - KLU. Ground leveling work is mostly done, sleepers and gravel has been stashed along side of track and the bridge work across the Penna River at KLU is almost done.
Pic...
more...
16 Posts
Yeah, I know the station but there weren't any works going on there.
I hope This Double Line Should Complete Soon So That People In That Region Can Reach Gooty In Few Hrs
Yeah, I hope so too. The works are being done at a decent pace, hopefully the day will come soon.