#ShiradiGhat
Located at 889 m above MSL, this is where the ghat section begins. It took 2 Hrs 45 mins to climb down 55 Kms. It has 57 tunnels in the span of some 45 Kms. Finally climbing down to 114 m.
Ticket is inflated by 55 Kms.
.
From...
more...
Located at 889 m above MSL, this is where the ghat section begins. It took 2 Hrs 45 mins to climb down 55 Kms. It has 57 tunnels in the span of some 45 Kms. Finally climbing down to 114 m.
Ticket is inflated by 55 Kms.
.
From...
more...
11 Public Posts - Sat Aug 04, 2018
1 Public Posts - Sun Aug 05, 2018
1 Public Posts - Wed Sep 26, 2018
Only OHE Foundation work completed at Kumta a month ago. OHE foundation work going on at between Block stations.
As per information , Poles have been laid in between Murudeshwar & Bhatkal stations & Padubidri station in Karnataka Part of KR. Work is going simultaneously everywhere & very fast as compared to rest of IR.
Last 2 Sundays, they had took Block for laying poles at above mentioned locations.
As per information , Poles have been laid in between Murudeshwar & Bhatkal stations & Padubidri station in Karnataka Part of KR. Work is going simultaneously everywhere & very fast as compared to rest of IR.
Last 2 Sundays, they had took Block for laying poles at above mentioned locations.
1 Public Posts - Wed Sep 26, 2018
2 Public Posts - Thu Sep 27, 2018