#Electrificationupdate of #Ballaricantt station - Part-2: Foundations for OHE portal / poles at Ballari Cantonment (BYC2)
🔸Photos captured on #August7th2018
⏺️Picture 1 shows 5 incoming lines of Ballari Cantonment
⏺️Out of these 5 lines, 2nd (up line) and 3rd lines (down line) are main lines. 1st, 4th and 5th lines are loop lines (Count all these lines from right to left)...
more...
🔸Photos captured on #August7th2018
⏺️Picture 1 shows 5 incoming lines of Ballari Cantonment
⏺️Out of these 5 lines, 2nd (up line) and 3rd lines (down line) are main lines. 1st, 4th and 5th lines are loop lines (Count all these lines from right to left)...
more...
31 Posts
Miraj-PVR electrification has been started. You can see poles on site. This is between Miraj and Dhalgaon.
AFAIK sub-stations are being constructed at Ballari Cantonment (BYC2), Kariganuru and Guntakal West
Thanks to Pratik’s rail zone...
Work is on good pace, but no signs at Pandharpur station so it seems miraj to Jawala only being electrified.
Work is on good pace, but no signs at Pandharpur station so it seems miraj to Jawala only being electrified.