Regarding electrification, from viramgam to chand lodiya , erection of single poles is complete but where ever mast profile are required like at station pfs and yards work is pending. ADI to chandlodiya already electrified
Rrgarding doubling, leveling work done is few and far less , and is being done in patches, like in the outskirts of Surendranagar and wanakaner.
From Viramgam upto chamraj lines have been laid.
Rrgarding doubling, leveling work done is few and far less , and is being done in patches, like in the outskirts of Surendranagar and wanakaner.
From Viramgam upto chamraj lines have been laid.