Update on the doubling and electrification in Kacheguda and Mahbubnagar route between Timmapur/TMX and Falaknuma/FM.
The ground leveling works have been started after TMX and are on full swing, most of the stretch is finished except some patches. Electric poles have been erected, till Umdanagar/UR. One bridge and one RUB are being constructed.
Between UR and Budvel/BDVL, the ground leveling is done, rails and sleepers have been laid except that the thermit welding hasn't been done.
Between...
more...
The ground leveling works have been started after TMX and are on full swing, most of the stretch is finished except some patches. Electric poles have been erected, till Umdanagar/UR. One bridge and one RUB are being constructed.
Between UR and Budvel/BDVL, the ground leveling is done, rails and sleepers have been laid except that the thermit welding hasn't been done.