Karnal_Junction^~ 1696 blog postsDelhi Rewari Section Electrification Status.
Electric Wires are being installed.
Platform 1 & Platform 3 Loop Lines are complete & Platform 2 Main Line is also Complete.
Down Main Line work in progress.
Status on...
more...
Electric Wires are being installed.
Platform 1 & Platform 3 Loop Lines are complete & Platform 2 Main Line is also Complete.
Down Main Line work in progress.
Status on...
more...
3 Posts
Recently Uday Express was launched and minister came only for inauguration of the train and multi level parking at Coimbatore. CRS is done when the work of electrification gets completed and the agency informs the DRM and they do CRS.
Nahi , ye right commission of railway safety board ke andar ata h , ulta election ki vajah se kam pura karne ka pressure h
Ab Election kahan se aa gaye Electrification ke beech mein. Aaj tak voter sirf Train do Vote lo ka logic use karti aayi hai lekin ab nahi hai railways mein aisa. All over India is waqt Electrification chal rahe hai.Gujarat ke election bhi khatam ho gaye hai lekin abhi bhi 1000 kms work hai aur Tamil Nadu mein abhi bhi 400+ hai Total overall India mein 6500+ kms hai in almost all the states except North East. So please don't compare railways with elections. Yes, Delhi-Jaipur is very important route and has been neglected for past several years, and electrification should have been done years ago. But during UPA they were interested in trains rather than Railway Development like more LHB rakes, More Gauge Conversion, More doubling and electrification. Even Raibarelli and Amethi are getting electrified now. So forget railways and election now.
Belive it or not election in sab cheez ko bahut effect karta h , goverment ne kya kya kam kiya h