Bandhuo, December 2017 se hi kumbh-2019 ke liye allahabad main city, naini area, phaphamau area me dabaa ke kaam chal raha hai.
Railway se related In kaamo mein jo kaam hai , wo hai kumbh ke waqt traffic congestion naa ho iske liye 7 level crossings pe ROB banaya jaa raha hai, 06 RUB ki width badhai jaa rahi hai, Ald pe Plt-11 ban raha hai aur sky walk se isko platform 1 etc se joda jaa raha hai, Prayag terminus stn jo neglected tha uska full renovation with 04 platform ban raha hai.
Jo...
more...
Railway se related In kaamo mein jo kaam hai , wo hai kumbh ke waqt traffic congestion naa ho iske liye 7 level crossings pe ROB banaya jaa raha hai, 06 RUB ki width badhai jaa rahi hai, Ald pe Plt-11 ban raha hai aur sky walk se isko platform 1 etc se joda jaa raha hai, Prayag terminus stn jo neglected tha uska full renovation with 04 platform ban raha hai.
Jo...
more...
3 Public Posts - Tue Sep 18, 2018
1 Public Posts - Wed Sep 19, 2018
1 Public Posts - Sat Sep 22, 2018
1 Public Posts - Sun Sep 23, 2018
1 Public Posts - Sun Sep 30, 2018
4 Public Posts - Fri Oct 12, 2018
2 Public Posts - Fri Oct 19, 2018
1 Public Posts - Sun Nov 11, 2018
7 Public Posts - Sun Nov 18, 2018
Ald east end to next 200 mtrs, no work done
200 mtrs to prayag, sleepers laid fully (see pictures above), May be by dec end or Jan end tracks may be laid fully.
Prayag to Pfm, only soil level is in progress, No sleepers laying till Ganga bridge remaining 04 spans gets ready. It will not complete anyway before Jun-Jul 2018.
200 mtrs to prayag, sleepers laid fully (see pictures above), May be by dec end or Jan end tracks may be laid fully.
Prayag to Pfm, only soil level is in progress, No sleepers laying till Ganga bridge remaining 04 spans gets ready. It will not complete anyway before Jun-Jul 2018.
10 Public Posts - Wed Dec 05, 2018