CRS inspection of Aishbag-Sitapur section, a part of the Lucknow- Pilibhit gauge conversion project being done by RVNL Lucknow unit
source url: click here
source url: click here
This CRS was for DAL/Daliganj - ASH/Aishbagh 7Km section including newly constructed single electric 450m line of MKG/ManakNagar - ASH/Aishbagh. Today is last day of 6 days mega block which was taken from 14-Sep to 19-Sep for DAL/Daliganj - ASH/Aishbagh section. Tomorrow 20-Sep-2018 speed trial will be conducted for said section. Post successful CRS MKG/ManakNagar - ASH/Aishbagh - LC/Lucknow City - DAL/Daliganj will be operational and 16 pairs of train and 5 pairs of DEMU/MEMU will be diverted on this route which will help in reducing the congestion at LJN/Lucknow Jn.