Budni - Itarsi 3rd line:
Budni - Hoshangabad: Track laying and linking completed at all places except few LCs, poles erected at most places, wiring left.
After Hoshangabad: Track laying+ linking+electric poles and Wiring also completed...except at LCs
ET-HBD 3rd line will be commissioned soon...
Budni - Hoshangabad: Track laying and linking completed at all places except few LCs, poles erected at most places, wiring left.
After Hoshangabad: Track laying+ linking+electric poles and Wiring also completed...except at LCs
ET-HBD 3rd line will be commissioned soon...