Search Forum
Blog Entry# 3911522
Posted: Oct 18 2018 (08:30)
7 Responses
Last Response: Oct 29 2018 (15:11)
7 Responses
Last Response: Oct 29 2018 (15:11)
Khetasarai Zafrabad Electrification #Crs done.
Electric freight soon frm Varanasi to Faizabad
जफराबाद से अकबरपुर व टांडा तक विद्युतीकरण का कार्य काफी समय पहले पूर्ण कर लिया गया है।
Electric freight soon frm Varanasi to Faizabad
जफराबाद से अकबरपुर व टांडा तक विद्युतीकरण का कार्य काफी समय पहले पूर्ण कर लिया गया है।
3 Public Posts - Thu Oct 18, 2018
Rest left electrification between Barabanki jn and Faizabad Jn 99.3 km section must be completed as soon as possible so that bsb to lko train can run on alcos.
Can somebody tell about progress of doubling and electrification between bsb to utratia Jn via Rai baraily.
Can somebody tell about progress of doubling and electrification between bsb to utratia Jn via Rai baraily.
2 Public Posts - Thu Oct 18, 2018
1 Public Posts - Mon Oct 29, 2018