This is the snapshot of the excel I made for Electrification progress till date. Please let me know if any changes are required or if there are any other sections were CRS took place but its not mentioned in the list.
(sections in green are newly added)
(sections in green are newly added)
203 Posts
Bareilly - Aligarh via Chandausi CRS Inspection was not done in FY 2018-19. So not updated them.
Ha filhaal electrification ka hi kaam chal Raha hai poles lag Gaye hai
Yesterday, I found a recent tender from RE Danapur division under CORE (dated 26th July 2019) mentioning that the work for the electrification of 79 RKM in Azimganj-New Farakka section including the wiring of the siding of Sonar Bangla Cement Factory & WBPDCL siding.