##Pics taken today 15th December morning after yesterday's successful CRS of BhagalpurJn to Lailakh Mamalka doubling (part of SBG Loop Doubling)
##Only 16 km lailakh Mamalka to Kahalgaon doubling left now in which 80% work has been completed and bridges are also completed.
##Interlocking to new track to BhagalpurJn is to be done after CRS report work on BhagalpurJn going on to lay tracks of sleepers and fixing them through support.