Dec 16 2018 (12:12) BAY/Ballari Junction (Bellary) (4 PFs)
SteelCityRF^~
SteelCityRF^~ 27568 blog postsRailfanning at #BallariJnouter on #December14th2018
🔸 #Electrificationupdate
⏺️Towards Guntakal
1) to 4) Poles with insulators were spotted untill 209.0 km
5) Foundations for OHE poles were spotted after 209.0 km
⏺️Towards...
more...
🔸 #Electrificationupdate
⏺️Towards Guntakal
1) to 4) Poles with insulators were spotted untill 209.0 km
5) Foundations for OHE poles were spotted after 209.0 km
⏺️Towards...
more...
12 Public Posts - Sun Dec 16, 2018
Yes they may go for that later after wiring of section or they may take it simultaneously with wiring works but construction of earth pits should be done well before as later they can only link that strip with track and that GI earth pit.