Dec 23 2018 (13:25) 06536XXX/Mysuru - KSR Bengaluru City Inaugural MEMU Special | MYS/Mysuru Junction (Mysore) (6 PFs)
Senthil
Senthil 1850 blog posts7 Public Posts - Sun Dec 23, 2018
10 Public Posts - Mon Dec 24, 2018
Substation at Y is indeed not ready. Earlier last year when FEDL was just complete, few trains mentioned above used to run w/ e-link. But since recently Chamundi, Rajya Rani was changed to e-loco and now SBC-MYS MEMU are running, transmission losses will only be higher. So there are 3 options w/ SWR as of now:
1. Keep running Chamundi + Rajya Rani w/ e links, and bear extra transmission losses
2. Pressurise KPTCL to complete work ASAP.
3....
more...
1. Keep running Chamundi + Rajya Rani w/ e links, and bear extra transmission losses
2. Pressurise KPTCL to complete work ASAP.
3....
more...