GUNTAKALLU -HOSAPETE Doubling RE #YearEnd Update SWR part -2
* erected OHE poles can be see btn 212.0km ballari outer (gtl side ) - 208.7 km durgamma gudi RUB
*only OHE foundation work can seen btn 208.7km - 202 .0 km byc2 in ballari city limits..
* erected OHE poles can be seen btn byc2 outer - kudutani ..here...
more... work going on fast pace ..
* only 13kms of line RE work completed btn kudutani (incl)-toranagallu (excl)
*RE wiring work yet to start TGNL ..OHE poles fixing work completed.
*only OHE foundation work can seen btn toranagallu- hosapete outer..
* Good news is that construction of substation (TSS) at kariganuru as began ..but unable take pic ..
*RE work yet to start near HPT
1.last pair of OHE poles before durgamma gudi RUB
2. OHE holes at PF3 BAY
3. OHE holes at PF1A BAY
4.OHE holes at PF2 BAY
but work yet to start at PF1 ..RE work looks challenging here dont know how they gonna workout .
5.SSP near mothi ROB BAY
6. Ballari fort view
7. ROB under construction
8. OHE foundation at BYC
9. TSS at BYC2
10. first OHE pole towards HPT after BYC2
11.OHE poles btn byc2 -kudatani
12. fully electrified at kudatani
13.fully electrified at daroji
14.wiring yet to start at TNGL
15. last OHE pole seen at TNGL towards HPT
16. this kind SSP is seen each & every station almost ..this one is near byalayodgere
17. TSS at Kariganuru beyond bush construction going on..
NOTE: RE work can be completed & opened by march 2019 for GTL -BAY-TNGL section
but main tough task will be
A. RE work HAGARI Bridge.
B. RE at BAY JN specially at PF1.
c. RE at BYC2 yard & TSS function.