Ajmer udaipur electrification DELAY #CRS on Mar-19: NWR GM REPORT !
Delay isliye hua hai ajmer Jaipur ke Eletricfication Abhi pura nahi hua hai or chittorgarh nimach dubling ke chalte chittorgarh station per new track dale ja rhe unka kam pura nahi hone se station per Eletricfication ka kam Ruka hua hai or nimach ratlam ke Crs inspection bhi Jun 19 me hone ki Umeeed hai. #Crs inspection Jaipur ajmer Chanderia chittorgarh udaipur Ratlam nimach ratlam fatehabad Sab ek sath kar sakte h
Delay isliye hua hai ajmer Jaipur ke Eletricfication Abhi pura nahi hua hai or chittorgarh nimach dubling ke chalte chittorgarh station per new track dale ja rhe unka kam pura nahi hone se station per Eletricfication ka kam Ruka hua hai or nimach ratlam ke Crs inspection bhi Jun 19 me hone ki Umeeed hai. #Crs inspection Jaipur ajmer Chanderia chittorgarh udaipur Ratlam nimach ratlam fatehabad Sab ek sath kar sakte h
5 Posts
Ratlam wale pata nahi q Dec ka wait kar rhe h jab ki section 189km ka hi or Wo bhi inse nahi ho rha.
Matlab poora root ek sath clear hoga tab to acha h kam se kam Elocos ka wait nhi karna padega pure root per ek sath Elovos run kar sakenge.
Dec. Ka wait is liye kar rahe h q ki abhi WR is root ke jyada tar satation ko modified kar rha h(Platform increasing,FOB,Painting,Parking) jisme time lagega is liye WR ye sab kaam hone ke baad hi Train chalana cahta h taki Station Ready rahe or Doubling ka bhi kaam baki h to ye bhi reason h.
I think due to doubling works in between COR-RTM. They are delaying electrification. They will complete electrification of COR and CNA, so that NWR bound trains can get e-locos and later on do the complete electrification of the double line till NMH and further to MDS-RTM route.
Wiring van CNA meaa chuki h umeed h jald hi wiring start jo jayegi.