Gooty- dharmavaram doubling: Travelled from gooty to anantapur today. Track has been laid from gooty cabin to turkhapalli.but electrification is pending.remaining portion turkhapalli to anantapur only land has been levelled. Sleepers and ballast has been procured. Between kalluru to garladinne in some places concrete beams has been laid and in some places pits are dig for laying concrete bases. Brides are almost in finishing stage and will be completed in next month.one bridge construction has to be started between garladinne and taticharla. New station building is under construction in garladinne/taticharla (forgot the station name) The total is expected to be completed by December 2020 or march 2021.
The progress looks to be slow, last time I checked, 9 months back, sleepers were laid after Gooty, a bridge near Kalluru was nearing completion. You can see my photos here
Yes the work is very slow . They have concentrated on GTL klu doubling and they left gy DMM and dhne pkl which is the main section