#Doublingandelectrificationupdate of Guntakal - Dhone section on #April7th2019
🔸Guntakal Junction - Mallappa gate - Maddikera - Tuggali
1) Land leveling done for doubling in patches
🔸Tuggali - Edduladoddi
2) Land leveling done for...
more...
🔸Guntakal Junction - Mallappa gate - Maddikera - Tuggali
1) Land leveling done for doubling in patches
🔸Tuggali - Edduladoddi
2) Land leveling done for...
more...
1 Public Posts - Fri Apr 12, 2019
1 Public Posts - Sat Apr 13, 2019
⏺️I have edited main blog, please check it, first photo shows doubling progress of entire Guntakal Junction - Mallappa gate - Maddikera - Tuggali section
⏺️I didn't observe any work from Mallappa gate towards Wadi line. I was sitting on SLB, so didn't capture photos on LB side. So I am not sure whether work has started or not
⏺️I didn't observe any work from Mallappa gate towards Wadi line. I was sitting on SLB, so didn't capture photos on LB side. So I am not sure whether work has started or not
2 Public Posts - Sat Apr 27, 2019