Journey Date: Tue May 28
Number of Members on this Trip: 1
SteelCityRF^~
SBC/KSR Bengaluru City Junction (Bangalore) --> BAY/Ballari Junction (Bellary)
Train Status: 1h 32m late
Last Update: @ BAY/Ballari Junction (Bellary) @ May 29 2019 (11:12)
Speed: 13 km/h
67 Posts
⏺️Wiring has been started for short distance for Chikjajur line i.e., 1.2 km
⏺️OHE poles with wiring are there for short stretch of bypass line towards Hosapete end. But OHE pole foundations/OHE poles are there for bypass line towards Chikjajur end
⏺️OHE poles with wiring are there for short stretch of bypass line towards Hosapete end. But OHE pole foundations/OHE poles are there for bypass line towards Chikjajur end
whether PF extension work completed at Rayadurga?
No. It is still under progress
please share pics ..if u hv
Ok. I will post them as soon as possible