#RAILWAYELECTRIFICATION - CORE ALLAHABAD
.
*** Quarterwise and Projectwise target for CORE (2019-20) ***
Reference: click here
.
Quarter-1...
more...
.
*** Quarterwise and Projectwise target for CORE (2019-20) ***
Reference: click here
.
Quarter-1...
more...
1 Posts
But most of Q1 targets will not be achieved as 2 months slowed work due to elections and some places retendering done due to slackness/ inefficiency of earlier company/firm
Much of the tasks are from last year unfinished work. So to make project more deadline oriented they had distributed it in Quarterly wise manner.
What is the current electrification status of Manigram-Tildanga in Q3?