रांची. रांची रेल डिवीजन के इंजीनियरों ने 70 घंटे के काम को महज छह घंटे में पूरा कर दिखाया। इंजीनियरों ने रेलवे क्रासिंग गेट को बंद...
Villagers and less educated peoples actually misunderstands this type of News!! And these news are very common now a days.
After reading this type of news, I saw/heard people demanding sub-way at their respective locations as it just takes 6 hrs!!
Many people don't understand, that the pre-work is done from minimum 2 months, concrete structures are prepared and kept ready. And if we go into the tender process, it takes about 6 months in all, and not 6 hrs.. Its just a block of 6 hrs that is being taken.
After reading this type of news, I saw/heard people demanding sub-way at their respective locations as it just takes 6 hrs!!
Many people don't understand, that the pre-work is done from minimum 2 months, concrete structures are prepared and kept ready. And if we go into the tender process, it takes about 6 months in all, and not 6 hrs.. Its just a block of 6 hrs that is being taken.