Hosapete-Bhanapura 40kms Double Electrification Update part of HOSAPETE-HUBBALLI-VASCO RE PROJECT:
* Poles are Erect Btn HPT-Ginigere but wiring not started .
*wiring work completed btn GINGERE(Excl)-Koppal (KBL) -124.6km-119.6km.
*Poles are Erect Btn Koppal-Bhanapura(Excl) but wiring not started .
*HPT(Excl)-Bhanapura(incl)...
more...
* Poles are Erect Btn HPT-Ginigere but wiring not started .
*wiring work completed btn GINGERE(Excl)-Koppal (KBL) -124.6km-119.6km.
*Poles are Erect Btn Koppal-Bhanapura(Excl) but wiring not started .
*HPT(Excl)-Bhanapura(incl)...