Jul 15 2019 (23:23) IMG26057-1766013/♥♥Jaipur - Ballari SF Express♥♥
2805 net green flags 12 green per TrainCustom Ratings
SWRailway^~
SWRailway^~ 242 img trains 204 popular2805 net green flags 12 green per TrainCustom Ratings
Please rate and give green flag given. There are many people from Rajasthan residing in Belagavi and Hubballi but there is not even a single direct train between Jaipur to Hubballi. So this will be a good train. Suggestions are welcomed. Thanks in advance.
19 Posts
Pits for OHE poles were observed only single line or for both lines? What is the status of doubling in Hubballi - Dharwad section?
From pics of deepak we can see their is RUB bridge widening of Gadag road taking place so after completion of that new double line can be joined to Hubli yard coming from unkal side. Usually In Hubli Dharwad stretch works goes slow as it's in city limits where land acquisition is bit tougher one.. Electrification of route is not big task compared to doubling which needs more expenditure and time too. After complete doubling they CORE can take RE of those doubled routes..
Yes but if RE completes until Hubli then Eloco will sure run until Hubli from GTL side so IMO Hubli will get Eloco from the route on which it won't care to run more passenger trains 🤣🤣🤣.. It should realize that the section which is being neglected for train facilities is ahead in good rail infra... Also section helps to get the profit to show RB that SWR in this much profit...
After ubl there is a rub after that till dwr for land levelling is in good progress but due to darkness couldn't observe properly. Regarding re in ubl ld section wherever still there is a single line only for that line ohe is being laid and ofcourse for double line section on both lines its been laid.
Ok. I was telling regarding electrification of MRJ - LD - UBL section not UBL - BAY section