Aug 22 2019 (07:18) AY/Ayodhya Dham Junction (3 PFs) | BRC/WAP-4/22810
KhagariaJn^~
KhagariaJn^~ 63460 blog postsCRS inspection of Mankapur Katra Ayodhya for 36 RKM was done on 21.08.19.
Total CRS inspection in 2019-20 by CORE is now 493 RKM. click here
Total CRS inspection in 2019-20 by CORE is now 493 RKM. click here
But this RE work is of no use as it does not include main Ayodhya Jn..the last pole is on the outer of AY where the NER line ends. This will serve no purpose as no loco can come upto Ayodhya Jn from Mankapur Jn side. NER and NR same old fight...when NR will do it's work no news on RE and Doubling...I tried to find out till barabanki..all single line and diesel line only.