Udaipur-Himmatnagar GC :- Work is going at rapid pace between Udaipur and Umarda, CRS is to be expected in the next month...
Pic No.1-2 :- Track packing machine standing near old pit line...
Pic No. 3-4 :- Extension of new pit line almost complete, only track laying is pending..
Pic No. 5-6 :- Signals have been installed towards Umarda side..
Pic...
more...
Pic No.1-2 :- Track packing machine standing near old pit line...
Pic No. 3-4 :- Extension of new pit line almost complete, only track laying is pending..
Pic No. 5-6 :- Signals have been installed towards Umarda side..
Pic...
more...
2 Public Posts - Sat Sep 21, 2019
4 Public Posts - Sun Sep 22, 2019
Bhai kaam to kafi acha h kya lagta h Pura root kab tak complete ho jayega?