Nov 03 2019 (16:48) 09679X/Udaipur City - Kota Special | KOTA/Kota Junction (6 PFs)
Love114~
Love114~ 1571 blog postsChanderia Kota eletricfication update 03-Nov-19
Foudation work almost 40% complete , bundi kota poles fixed wiring due.
Poles work 30% complete
Dec-19 target on foudation and singal upgration on 100%.And poles work 60% complete.
...
more...